A subcontractor is qualified on the process rather than on a sample. Fudiesel visits for plating, machining or welding work, checks the equipment and the records, and asks for the inspection method that will be used on the parts. A sample is then run and measured against the drawing before any production order is placed. Where the work is a special process such as passivation, the certificate is checked for the actual bath and the date, not just for the result. A supplier who cannot show a record is treated as unqualified, since a good part with no evidence cannot be defended in a claim. The visit is repeated whenever the process or the equipment changes. Final specifications are subject to the written quotation or contract.